Curbed LA: Dramatic revamp of Redondo Beach waterfront put on hold

“Redondo Beach’s plans to dramatically remake its waterfront are on hold.

“A court ruling says a key document in the planning process must be altered and re-distributed to the public before the project can get underway.

“Los Angeles Superior Court Judge James Chalfant has ordered a number of revisions to the project’s final environmental impact report in response to a lawsuit filed by Building a Better Redondo, which sued the city of Redondo Beach to stop the project.”

Angel Law is proud to represent Building a Better Redondo in this matter.

https://la.curbed.com/2018/5/18/17366684/redondo-beach-pier-waterfront-revamp